 Plan-wise Expenditure & Benefits Minimize Maximize 

Expenditure and benefits of Major and Medium Projects


 

Plan Period

Expenditure Incurred
(Rs. in Crore)

Potential Created
(Lakh Ha)

During

Cumulative

During

Cumulative

Pre Plan---25.53
First Plan ( 1951-56)30.8130.813.3028.83
Second Plan (1956-61)25.4356.242.7131.54
Third Plan (1961-66)54.90111.143.5735.11
Annual Plan (1966-69)48.93160.070.9636.07
Fourth Plan (1969-74)172.48332.554.7340.80
Fifth Plan (1974-78)371.59704.1411.1751.97
Annual Plan (1978-80)296.081000.223.9755.94
Sixth Plan (1980-85)924.261924.486.2162.15
Seventh Plan (1985-90)1245.013169.494.4366.58
Annual Plan (1990-91)300.443469.930.8367.41
Annual Plan (1991-92)215.5236.850.4867.89
     
Eight Plan (1992-97) Proposed2599.34-8.84-
Annual Plan (1992-93)284.743970.190.5468.43
Annual Plan (1993-94)309.004279.190.6369.06
Annual Plan (1994-95)300.804579.990.1269.18
Annual Plan (1995-96)317.854952.990.5669.74
NABARD +55.15---
Annual Plan (1996-97)*299.835423.450.6970.43
NABARD +104.09---
AIBP +66.54---
Eight Plan (1992-97) Actual1738.225423.452.5470.43
NABARD +159.24---
AIBP +66.54---
     
Ninth Plan (1997-2002) Proposed2600.12-10.00-
Ninth Plan (1997-2002) Anticipated3248.898672.3410.0080.43
Annual Plan (1997-98) Actual276.275897.321.2971.72
NABARD +89.35---
AIBP +108.25---

 

 Irrigation Department Uttar Pradesh, Government of Uttar Pradesh, Lucknow.